Maharashtra Samruddhi Mahamarg Package-2

Afcons was the first contractor to complete Pavement Quality Concrete (PQC) of an entire package (PKG-2) in Maharashtra Samruddhi Mahamarg, and emerged as the first contractor to complete its work ahead of schedule. Here are some important facts & figures of this project

58.4km stretch from village Khadki Amgaon to village Pimpalgaon in Wardha district
First package of Samruddhi Expressway to be completed ahead of schedule
• Design speed of 150kmph
• Highly structure intensive project: More than 200 structures
53 box culverts, 25 minor bridges, 19 vehicular underpasses, 12 pedestrian underpasses, 11 flyovers, five major bridges, two rail over bridges, two wildlife overpasses, two wildlife underpasses
Country's first wildlife overpasses, one of the widest in Samruddhi Mahamarg and perhaps also in India
• Two wildlife overpasses with a pier height of 27m each
12km open hill cutting totalling 10 million cum
18 million cum of total earthwork
80m span steel structure erected on both carriageways for bow string bridge
315m-long major bridge over Wardha river completed in 14 months
330m-long six-lane flyover completed in 16 months
2 interchanges in the project with 1 interchange having a total length of over 13km
1 rotary with 46 slabs

 