Kanpur Metro
Merely three-and-a-half months following the inauguration of the Priority Section of Kanpur Metro project, Afcons successfully erected the first Pier Cap of the corridor.
Key numbers
The Pier Cap was erected on Pier 19 between IIT Kanpur and National Sugar Institute
The Pier Caps are 2m in height, 9.3m in length, 2.8m in width, and weigh about 70 tonnes
More than 600 Piles and 42 Piers have been completed in the section
24 U-Girders and 10 Pier Caps have already been cast